The below content is licensed according to Creative Commons Attribution-ShareAlike License contrary to the public domain logo at the foot of the page. It originally appeared on http://en.wikipedia.org. The original article might still be accessible here. You may be able to find a list of the article's previous contributors on the talk page.

Leslie Barns (formerly known as Ashbridges Bay Streetcar Maintenance & Storage Facility)[1] is a light rail vehicle storage and maintenance facility under construction for the Toronto Transit Commission in Toronto, Ontario, Canada to house and service its 204 Flexity Outlook light rail vehicles.[2]

Six sites were considered and Toronto City Council made the final choice of surplus land at Ashbridges Bay Wastewater Treatment Plant, at the southeast corner of Leslie Street and Lake Shore Boulevard, on November 11, 2009. While the existing Roncesvalles Carhouse and Russell Carhouse will house some of the vehicles, the maintenance facilities at these older facilities cannot accommodate the new vehicles, which are considerably longer than the TTC's current streetcar fleet.[3][4][5][6]

The site is 22 acres and construction was projected to cost $345 million CAD in June 2009.[5] The carhouse will cover 4.3 acres.[7] The first of the new streetcar vehicles are scheduled to enter service in 2013–2014, and the carhouse is scheduled to be ready to service them.[4]

The facility will include a 250 metre brake test track.[7]

Construction of the spur, from the facility, to Queen Street, began in September 2013.[8][9] The construction was projected to require 12 weeks of road closures.

The other five sites under consideration were[2]:

The facility is budgeted at $497 million CAD.[10]

References

  1. Leslie Barns (formerly known as Ashbridges Bay Streetcar Maintenance & Storage Facility)
  2. 2.0 2.1 "New Light Rail Vehicle (LRV) Maintenance & Storage Facility - The Site". City of Toronto. November 29, 2009. http://www.toronto.ca/involved/projects/lrv/site.htm. Retrieved March 15, 2012.  mirror
  3. Natalie Alcoba (February 2, 2011). "TTC moving ahead with new facility in Leslieville". National Post. Archived from the original on March 21, 2013. http://www.webcitation.org/query?url=http%3A%2F%2Fnews.nationalpost.com%2F2011%2F02%2F02%2Fttc-moving-ahead-with-new-facility-in-leslieville%2F&date=2013-03-21. "Staff are willing to look at housing some of the vehicles at the Hillcrest yard, or the Exhibition Loop, but say the Ashbridges site is necessary for, at the very least, maintenance. The plan is already nine months delayed, and deferring Wednesday’s decision by 90 days means the soil removal work cannot begin until August because of migratory birds." 
  4. 4.0 4.1 "New Light Rail Vehicle (LRV) Maintenance & Storage Facility". City of Toronto. February 22, 2012. http://www.toronto.ca/involved/projects/lrv/. Retrieved March 15, 2012.  mirror
  5. 5.0 5.1 David Nickle (June 11, 2009). "TRANSIT: TTC looking to Portlands for its storage facility". Durham Region. http://www.durhamregion.com/print/36960. Retrieved March 16, 2012.  mirror
  6. David Nickle (June 18, 2009). "EAST TORONTO: Residents not happy with possible LRV facility". Inside Toronto. http://www.insidetoronto.com/insidetoronto/article/74464. Retrieved March 16, 2012.  mirror
  7. 7.0 7.1 Nigel Terpstra (November 23, 2012). "Everything You Ever Wanted to Know About TTC's New 'Leslie Barn'". Urban Toronto. Archived from the original on March 21, 2013. http://www.webcitation.org/query?url=http%3A%2F%2Furbantoronto.ca%2Fnews%2F2012%2F11%2Feverything-you-ever-wanted-know-about-ttcs-new-leslie-barn&date=2013-03-21. "Another vital but less-talked about piece of Toronto's evolving transit network is the Ashbridges Bay Streetcar Maintenance & Storage Facility, recently redubbed 'The Leslie Barn.' This 279,463 square foot facility will be sited on a piece of vacant land at the southeast corner of Leslie Street and Lake Shore Blvd." 
  8. "Leslie Street closure at Lake Shore Boulevard expected to last 12 weeks". Inside Toronto. 2013-09-19. Archived from the original on 2013-09-23. http://www.webcitation.org/query?url=http%3A%2F%2Fwww.insidetoronto.com%2Fnews-story%2F4115466-leslie-street-closure-at-lake-shore-boulevard-expected-to-last-12-weeks%2F&date=2013-09-23. Retrieved 2013-09-23. "The TTC was expecting a 12-week closure of Leslie Street immediately north of Lake Shore Boulevard to begin as soon as this week." 
  9. "Leslie Barns: September 13, 2013 - Construction Update, Closure on Leslie Street". Toronto Transit Commission. 2013-09-13. Archived from the original on 2013-09-23. http://www.webcitation.org/query?url=http%3A%2F%2Fwww.ttc.ca%2FAbout_the_TTC%2FProjects%2FLeslie_Barns%2Fnews.jsp&date=2013-09-23. 
  10. Chris Kitchings. (June 20, 2013). "New streetcars will roll out on Spadina, Bathurst first". CTV News. http://toronto.ctvnews.ca/new-streetcars-will-roll-out-on-spadina-bathurst-first-1.1332068. Retrieved June 20, 2013. "According to the implementation plan, the capital costs for the streetcars and upgrades have surpassed $2 billion. That figure includes the $1.1-billion price tag for the streetcars themselves, $497 million for a new Leslie Street facility where the streetcars will be stored and maintained, and infrastructure modifications."